Portions where toilets come at First Floor level were concreted earlier at lower level to facilitate easier plumbing work.Rest of the portions which forms major area was concreted using ready mix concreting on Sunday,Nov 22.Pictures after concreting when water retained curing is done follows
3600 sft two storeyed house with two independent houses on each floor at Elamakkara,Cochin for USA based NRI
Thursday, November 26, 2009
Saturday, November 14, 2009
Ground Floor roof slab concrete work in progress
One more portion above servant tolet is concreted as sunken slab for betterpipe laying for pumbing work.Balance portion roof slab work in progress.Pictures show work in progress
Wednesday, October 7, 2009
Brick work completed,part of roof concrete
Brick work upto roof level conmpleted,part of roof slab where roof has to come at a lower lowel due to toilets coming directly above also concreted.Pictures show work in progress.
Tuesday, September 29, 2009
Brick work reaching Ground Floor roof level
Pictures show work in progress as brick work reaches ground floor roof level.At 255 cm level,above car porch and sit out,beams come as support for slope sunshades to come.A few more areas brick work has to reach roof level and then flat roof slab concrete work can start
Labels:
Brick work reaching roof level
Sunday, September 20, 2009
Lintel,flat sunshades ,lofts and stair concreting
A loft is concreted above servant toilet and work area for storage of items not required on day to day affairs with access from kitchen and living room.These access will be closed with woodden shutters at a later stage.
There is also a loft with access from rear side of house above the gap in the rear side for keeping materials like working tools etc required at outside of house.This will not have woodden shutter and will be freely accessible from rear portion of the house
Sunday, September 13, 2009
Saturday, September 5, 2009