3600 sft two storeyed house with two independent houses on each floor at Elamakkara,Cochin for USA based NRI
Wednesday, October 7, 2009
Brick work completed,part of roof concrete
Brick work upto roof level conmpleted,part of roof slab where roof has to come at a lower lowel due to toilets coming directly above also concreted.Pictures show work in progress.
Tuesday, September 29, 2009
Brick work reaching Ground Floor roof level
Pictures show work in progress as brick work reaches ground floor roof level.At 255 cm level,above car porch and sit out,beams come as support for slope sunshades to come.A few more areas brick work has to reach roof level and then flat roof slab concrete work can start
Labels:
Brick work reaching roof level
Sunday, September 20, 2009
Lintel,flat sunshades ,lofts and stair concreting
A loft is concreted above servant toilet and work area for storage of items not required on day to day affairs with access from kitchen and living room.These access will be closed with woodden shutters at a later stage.
There is also a loft with access from rear side of house above the gap in the rear side for keeping materials like working tools etc required at outside of house.This will not have woodden shutter and will be freely accessible from rear portion of the house
Sunday, September 13, 2009
Saturday, September 5, 2009
Monday, August 31, 2009
Brick work reaching lintel level
Brick work is reaching lintel level.Doors and windows are also being fixed along with brick work.29 rectangular columns are being concreted along with raising of brick work.These are projections of original concrete piling columns.Out of the total 31 pile columns two coming up in sit out area are being raised up as round columns.
A half HP motor is purchased and fixed with all acessories like suction and delivery hose for pumping water from well to be used for construction and related curing work.Pictures show work in progress
Labels:
Brick work reaching lintel level