Friday, March 20, 2009

Concrete piling continues







We have completed 24 piles as on date leaving 7 more to be done.Pictures show work in progress

Wednesday, March 18, 2009

Piling continues




Piling has now reached 18 Nos leaving 13 more to be done.Pictures show work in progress

Wednesday, March 11, 2009

Piling work continues
















Pictures show reinforcement of steel being placed in pile pit and sections of pipes being placed one after another before concrete is poured into the pile pit.Nine pile concreting already over and piling expected to be completed in two weeks

Friday, March 6, 2009

Piling work
















Piling work commenced today with one pile concrete completed and digging for another pile in progress.Pictures can be seen

Thursday, March 5, 2009

Piling work starts











Welding of steel reinforcement for piling already started.Cement and other concrete aggregates arranged at site.Piling work starts from 6,March.Pictures shows site activities for piling

Well


Well is constructed at north east corner of the plot for taking water for construction.Picture shows well

Temporary shed


Temporary shed is made with palm leaves can be seen in pic.This shed will be used for keeping cement and working tools in addition to acting as temporay accomodation for workers