Tuesday, February 24, 2009

Site clearing,levelling




Temporay shed construction for keeping cement,protecting electric connection and for keeping tools and stay of workers whenever required is constructed today.Site is cleared of all growth and when the bushes were removed,a pit was found on the surface.To fill it up 6 Nissan loads of gravel is used.Pictures show gravel being filled up and temporary shed work in progress
On 26/2,site sit out will be done prior to piling followed by steel work for piling

No comments:

Post a Comment