Pictures show red sand being filled inside foundation beam which forms part of basement of the building
3600 sft two storeyed house with two independent houses on each floor at Elamakkara,Cochin for USA based NRI
Wednesday, July 22, 2009
Saturday, July 18, 2009
Foundation beam work completed
Foundation beam work is completed.Next,foundation has to be filled and height of basement to be raised first with brick for a height of 25cm and then provide Damp proof concrete on top of basement to prevent water seeping into floor of the house later.Basement brick work will be plastered inside.After filling up this raised portion of basement,brick work for walls will start
Friday, July 10, 2009
Friday, July 3, 2009
Wednesday, July 1, 2009
Foundation beam
After piling,pile chipping,filling the plot,levelling the plot,red sand is again filled to raise land and to provide stable support for foundation beams also usually called as plinth beam.Plinth beam acts as the support base for all walls of the building.Pictures show reinforcement steel work for plinth beam.Plinth beam in this case is of 40cm height and 25 cm width.Concreting of Plinth beam is expected to be completed by 5,July,09