Saturday, July 18, 2009

Foundation beam work completed

Foundation beam work is completed.Next,foundation has to be filled and height of basement to be raised first with brick for a height of 25cm and then provide Damp proof concrete on top of basement to prevent water seeping into floor of the house later.Basement brick work will be plastered inside.After filling up this raised portion of basement,brick work for walls will start